Case Study
North Middlesex
University Hospital
Call 01603 594 984 Installation of a of a 199.8 Kwp PV System, comprised of Trina Solar Panels, K2 mounting system and SolarEdge optimisers and inverters.
Scope of works:
- Installation of Solar PV system
- Installation of LV mains distribution and supplies
- AC/DC containment

6 Weeks
Circa £220k
North Middlesex
"I just want to take the opportunity to thank you and everyone at AME for all your support and the quality you’ve delivered throughout the project."